NIMAR - Announcements /Notices/ Clarifications

Active Bids

Final Evaluation Report (PID (I) No. 1937/25)

Technical Evaluation Report

CORRIGENDUM , Invitation to Bids, Last Date: Thursday 2nd October 2025 by 1100 Hrs

Invitation to Bids, Last Date: 1100 Hrs, 22nd Sep, 2025   (Bidding Document)

Qureies and Clarifications

S. No.

Obscure Name

Question

Answer

1

Bidder A

In Lot III item 1, Photocopier machine your require 32CPM A3 speed, its mean we have to quote above 60 CPM copier to meet this speed and second please clarify that you need Drum life 3 Million copies or 300,000 copies. As the heavy duty copiers have extended drum life which ensure lowest TCO.

1. The required specification is 36 CPM A4 and 18 CPM on A3.
2. Minimum drum life of 300,000 Copies

2

Bidder B

1. In LOT-III, Sr. No. 6.3.1, the specifications mention 36 CPM at A4 and 32 PPM at A3. This appears to be a typographical error, as photocopiers with 36 CPM at A4 typically offer only around 18–19 PPM at A3. We kindly request clarification or correction of this specification to avoid confusion during evaluation.

2. The specified drum life of 300,000 pages is highly brand-specific and not commonly available through most authorized distributors. We recommend either, Removing drum life from technical evaluation and instead requesting cost per click, or Revising the requirement to 100,000 pages, which aligns with industry norms and ensures fair, competitive bidding.

3. Most 36 PPM (A4) copiers in this category are equipped with up to 250 GB HDD. We suggest revising the requirement to allow 128 GB SSD or 250 GB HDD, which reflects the typical configurations offered by major brands.

4. We recommend allowing item-wise quoting for LOT-III or restructuring the lot accordingly.

1. The copying speed should be 36 cpm or higher on A4 and 18 cpm or higher on A3.
2. The minimum drum life of 100.000 Copies (This will supersede of clarification # 1(2)).
3. Please follow the bidding document
4. Please follow the bidding document

3

Bidder C

For turnkey solutions, we request leniency in the marking criteria. This clause alone carries 25 marks, which is a significant portion of the overall evaluation. Kindly consider excluding this clause to ensure fair and broader competition among participants. Looking forward to your favorable response.

1. Please Follow the bidding document

4

Bidder C

We need your guidance and clarification on the following points related to the IESCO load sanction process: Who will be responsible for obtaining approval of the Load Sanction from IESCO? Who will deposit the Demand Notice? Who will deposit the Security? Who will provide the Metering Panel? Is the pole with H-Type Frame available on site? Who will provide the HT Cables? Additionally, we request an extension of this bid at least 15 days. Your timely response on these matters will help us plan and proceed accordingly.

1-3. Bidder will be responsible to complete all the formalities with IESCO including, But not limited to approval of sanction of load,demand notice and security deposit.
4. Bidder will provide the metering panel and is responsible for end to end deployment
5. No pole with H-Type frame is available on site. Bidder will be responsible to arrange all the items needed to fullfil the deployment needs.
6. Bidder will provide HT Cables.
7. Please Follow the bidding document

5Bidder CRack A: 8-core splice Rack B: 8-core splice First Floor: 8-core splice

Query 1: The MMR is connected to Rack A and Rack B using 8+8 core splices. • Is this capacity sufficient for PR site requirements? • Can the same configuration be replicated at Dr site?

Query 2: The First Floor is connected to the MMR via an 8-core splice. • Is this sufficient for PR site requirements? • Should the same setup be mirrored at the DR site?

Query 3: 2. Power Plant to NetEco Server Connectivity A 4-port ODF is already installed and connected at both ends (Power Plant and NetEco Server). Is this configuration adequate for the PR site? Should the same be implemented at the DR site for consistency?

Query 4: NOC Connectivity The NOC is already connected to the switch installed in the Data Center. Is a separate ODF required in the NOC? If yes, please specify the destination or termination point for the other end of the ODF.
1. Yes the capacity is sufficent for Path A. There is no DR site mentioned in RFP. 2. No such requirements
3. We require a seprate path for PATH B
4. No such requirement
5. The ODF will be deployed on an as-need basis to ensure optimal connectivity where required. *These clarification responses are applicable to all bidders.
6Bidder CQuery 5: Additional Connectivity If any other connectivity is required, please elaborate for both ends to ensure proper planning and implementationPlease follow the bidding document
7Bidder CPage 62 Item 11Bidder must provide the GA drawings of every proposed panel as per the proposed Single Line Diagram with details like Breaker Rating, Quantity of Components, internal spacing details. Cross sectional area and IEC 61439-1&2 standards-tested and compliant for greater safety, reliability and maintainability.Need to amend as local standards will be apply because these are not imported Types Tested panel and no Test report will be available.Please follow the bidding document
8Bidder CTransformer PAD Mounted. Who will get approval of Load sanction from IESCO?
Who will deposit the Demand Notice ?
Who will Deposit Security? Who will provide Metering Panel?
Who will provide HT Cables?
What is Warranty on below Items as normally these items have One Year Warranty. AVR Gen Set Transformer Panel warranty. AVR IP 65 mentioned in RFP which will be required to Change in IP54. Need Clarification on Spare Parts Prices as mentioned on BID Page 31. Normally AVR comes with RS 485 Modbus so allow this as well. AVR response time mentioned in RFP 10M/s so allow 10m/s to 30m/s, as normally AVR Response time fall between 10-30m/s. Is customer has spare ports in Existing DCIM to configure new Equipment?

Page 61 11kv, 630Amps 4way switch with complete accessories. Need SLD and complete operational detail.

Page 61 Outgoing 45 x40A2-pole MCBs, 3phase &N Copper bus bars, Need SLD and complete operational detail.
1. A pad-mounted transformer with canopy shall be preferred.

2-4. The bidder shall be responsible for completing all formalities with IESCO, including, but not limited to, the approval of load sanction, demand notice, and security deposit.

The bidder will provide the metering panel and is responsible for the end-to-end deployment.

No poles with H-Type frames are available on site. The bidder shall be responsible for arranging all items necessary to meet the deployment requirements.

The bidder will provide HT cables.

A one-year warranty is required; longer warranties will be advantageous to the bidder. Please follow the bidding document.

Please follow the bidding document. *These clarification responses are applicable to all bidders
9Bidder CProvision and installation of 01 Generator Sync panel, for 2x250KVA generators, completed in all respects: Specifications: a. Panel Outdoor/floor standing, powder coating, b. deepsea module, with auto phase reversal/failure protection, c. SPD, indication lamps and MOR (if required). MOR is dedicated build in or external MOR? Rating/Tier III need external type MOR for Gen-sets backup operations during the serviceability and maintainability period both including MTTR/MTBF etc, Kindly elaborate clearly? Expansion provision for future 3rd Genset and controller from day one? Over-All Electrical Single-Line-Diagram must be endorsed by CDCP or (CTDC) Certified Tier Design Consultant or (ATD) Accredited Tier Designer with having Experience of 10+ TIER III Data Centers Industry?1. External MOR will be prefered.
2. There is no such requiremnet of third genset please follow the bidding document.
3. Electrical SLD must be endorsed by a PEC-registered Electrical Engineer.

*These clarification responses are applicable to all bidders.
10Bidder CPage 61 Outgoing 45 x40A2-pole MCBs, 3phase &N Copper bus bars, Need SLD and complete operational detail with end point connectivity of device/load/nodes.?The listed components shall be incorporated into the existing NIMAR SLD, and the updated SLD shall be provided. *These clarification responses are applicable to all bidders.
11Bidder CCould you please clarify what is meant by "set" in the quantities? We have noticed that the servers and network components do not have quantities mentioned, which is causing some confusion on our side. Kindly guide us so we can proceed accurately.1. The term “set” refers to a complete unit along with all required accessories and components necessary for its proper functionality. This definition applies uniformly to all items where the quantity is mentioned as set.

*These clarification responses are applicable to all bidders.
12Bidder CDear Sir, For LOT 1 and LOT 3, certain items require a 1-year warranty. Could you please confirm whether the performance guarantee for these line items should also be for 1 year, or still for 3 years?1. The performance guarantee will be fixed as per lots. *These clarification responses are applicable to all bidders.
13Bidder CTechnically for 400kVA AVR and required PMT Transformers, an upgraded system needed for 4C-185mm2 with 1C-5mm2 cables which seems surely under-sized cables for 400kVA system support. Correct operation of 400kVA system needs end to end upstream to downstream AVR onwards @240mm2-300mm2 Single core (5 including 4C + 1C Earth) is right sized approach, kindly advise the best? • Normally AVR comes with RS 485 Modbus dedicated built-in so allow this as well? • AVR response time mentioned in RFP 10M/s so allow 10m/s to 30m/s, as normally AVR Response time fall between 10-30m/s, allowed? • Do DCF have spare ports in Existing DCIM to configure new Equipment or that needs to be added from OEM as well as not mentioned anywhere as part and parcel of RFP?1. As per RFP, cable size shall be 4C-185mm² with ECC 1C-95mm².
2. Built-in RS-485 Modbus is acceptable in addition to SNMP for monitoring.
3. Response time shall be preferably 10ms but not exceeding 20ms.
4. Any additional modules, ports, or licenses required for DCIM integration shall be provisioned by the bidder. Please follow the bidding document

*These clarification responses are applicable to all bidders.
14Bidder CWhat is Warranty on below Items as normally these items have One Year Warranty? Or three Years including Critical Spares? o AVR o Gen Set o Transformer o Switchboards.
• AVR IP 65 mentioned in RFP which will be required to Change in IP54, please elaborate clearly?
• Need Clarification on Spare Parts Prices as mentioned on BID Page 31?
• As per Site, Existing Second ATS B is 400Amps up and running without any change needed, Change is only needed if it is needed to upgrade for suppling 400kVA AVR and 400kVA Transformer load support which means it needs end to end upgrade including contactor and Busbars/cubical including cables upgrade upto 600-800Amps system. Do the PATH B planning is shared or dedicated type for new induction of system for non-critical aux load? kindly confirm to avoid undercapacity planning at design phase from day one, right sizing is crux?
1. Warranty shall be three (03) years including critical spares.
2. IP65 shall remain mandatory as specified in the RFP for outdoor environment protection.
3. It is a typographical error—Path-B AVR shall be 250 kVA with identical specifications and performance to Path-A.

*These clarification responses are applicable to all bidders.
15Bidder C• Transformer is PAD Mounted? Or Pole Mounted only?
• Always Dry-type / Oil Immersed PAD Mounting Transformer are recommended as per TIER III/Rating III conformance, if still need PMT (Pole mounted transformers),it should be used in dedicated Indoor placement in sub power house constructed room separately?
• Dedicated location of New Sub power-house for new Transformer constructed room separately?
• Separate Dedicated location of New Sub Metering Panel constructed room separately for new Transformer?
• How to comply TIER/RATED III Future design on upstream side for the existing Legacy old Path A shared Powerhouse and existing PMT Transformers arrangements without new dedicated additions as asked for PATH B?
o Who will get approval of Load sanction from IESCO?
o Who will deposit the Demand Notice ?
o Who will Deposit Security?
o Who will provide Metering Panel?
o Who will provide HT Cables?
1. A pad-mounted dry-type transformer with canopy shall be preferred.
2. Possible locations have already been shared with bidders during the site survey; however, the final location remains subject to coordination with Radio Pakistan Electrical Team.
3. All other items will be provided by the biidder.

*These clarification responses are applicable to all bidders.
16Bidder DPlease clarify as below as per INVITATION TO BIDS Bid Security: PKR 4M for Lot I PKR 6M for Lot II PKR 0.2M for Lot III But as per BDS page # 47 13. 18.1 The amount of Bid Security shall be fixed RKR 1 Million. Which one can be considerable?1. The figure mentioned in BDS page #47 is a typographical error. The correct Bid Security amounts are as stated
PKR 4 Million for Lot I
PKR 6 Million for Lot II
PKR 0.2 Million for Lot III

*These clarification responses are applicable to all bidders.
17Bidder C• Page 61 11kv, 630Amps 4way switch with complete accessories If its dedicated MV substation is needed? o MV substation replacement of existing legacy system with new sourcing Path A as well overall with addition of New B path? Which must come with MTTM and bus coupling feature for double bus bar system? External Bypass needed? Dedicated dual MV Power House Construction of Halls on compartmentalized approach separately? Is it surely needed to meet TIER/RATING III compliance in future? Please give us conceptual SLD and complete operational detail.? • Page 61 Outgoing 45 x40A2-pole MCBs, 3phase &N Copper bus bars, Need SLD and complete operational detail with end point connectivity of device/load/nodes.?1. Replacement of legacy MV substation is required.
2. Path-A shall remain unchanged, and a new path shall be established for Path-B.
3. Same place shown during site survey will be used.
4. Please follow the bidding document
5. External bypass required for maintainability.
6. Conceptual SLD shall be submitted by successful bidder
18Bidder C• Page 62 Item 11Bidder must provide the GA drawings of every proposed panel as per the proposed Single Line Diagram with details like Breaker Rating, Quantity of Components, internal spacing details. Cross sectional area and IEC 61439-1&2 standards-tested and compliant for greater safety, reliability and maintainability? • What about serviceability? • Need to allow local assembled of cubical(s) will be applied because these are not imported Types Tested panel and no Test report for Cubical is available.?Please follow the bidding document
19Bidder CDear Sir, We would like to request an extension for the submission, as there are several ground surveys still required. The passive survey has been completed; however, the power survey is still pending. We kindly seek your support in granting us an extension of at least 15 days to complete the remaining work and submit accordingly. Looking forward to your favorable response.Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs
20Bidder DDear Concern, We sincerely appreciate the opportunity to participate in this project. After carefully reviewing the requirements, our team is confident that we can design and deliver a robust, efficient, and future-ready solution tailored to your specific needs. Since our priority is to ensure the highest quality standards, we want to dedicate adequate time for in-depth analysis, solution design, and validation of all technical and commercial aspects. This will allow us to address your requirements comprehensively, minimize risks, and present a proposal that delivers maximum value and long-term benefits. In light of this, we kindly request an extension of two weeks to finalize and submit our proposal. We firmly believe this additional time will enable us to put forward the best possible solution aligned with your expectations. We truly value your support and understanding, and we remain committed to delivering excellence.Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs
21Bidder Eit is requested you to kindly extend bid submission date for 2 weeksBid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs
22Bidder FTo conclude our proposal, our team visited on 17th Sept for Survey and found that still couple of clarifications like final location for placement of Gen Set, ATS and AVR yet to finalize by 19th Sep which are very critical for our input. Further certain equipment prices are still awaited from manufacturers. Would request you to extend the bidding time by 1 Week i.e. 29th September 2025.Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs
23Bidder GWe are pleased to participate in the subject tender for Procurement of IT Equipment. To prepare an accurate and competitive offer, we and our principal require additional time for special price approval. We kindly request an extension of the tender submission date by two weeks. We look forward to your consideration.Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs

Final Evaluation Report “GPU Server”to Bids, Last Date: June 16, 2025   (Bidding Document for GPU Server)

Final Bid Evaluation Report “Establishment of Disaster Recovery Site, IT &Allied Equipment (Information System, IT & Allied Equipment)”

GPU Server, FINAL EVALUATION REPORT

DR Site Technical Evaluation Report, Dated: April 25, 2025

GPU Server Technical Evaluation Report, Dated: April 25, 2025

Invitation to Bids, Last Date: March 26, 2025   (Bidding Document for GPU Server)

*Reference Advertisement/Corrigendum vide PID (I) 5381/24 published on 8th Feb 2025 regarding RFP titled “Establishment of Disaster Recovery Site, IT &Allied Equipment (Information System, IT & Allied Equipment)”. Bid opening venue has now been changed from “Room # 4058, 4th Floor, Cabinet Block, Islamabad” to “First Floor NIMAR, Pakistan Broadcasting Corporation Headquarters, Constitution Avenue G5, Islamabad."

*Bid submission on EPAD Portal is mandatory.

CORRIGENDUM 3, Invitation to Bids, Last Date: February 24, 2025

Revised RFP for Disaster Recovery Site and IT Equipment NIMAR, Last Date: February 17, 2025

ADDENNDUM, Invitation to Bids, Last Date: February 17, 2025

CORRIGENDUM 2, Invitation to Bids, Last Date: January 30, 2025

CORRIGENDUM 1, Invitation to Bids, Last Date: January 15, 2025

Invitation to Bids, Last Date: December 31, 2024   (Bidding Document)

*Bidding Document Fee is mandatory for submission of proposal.

*Bidding documant(Hard copy) may be collected from NIMAR office, first floor, Pakistan Broadcasting Corporation, G-5, Constitution Avenue, Islamabad, Pakistan

*All queries and clarification regarding RFP will also be entertained through EPADS portal till December 29, 2024

Qureies and Clarifications

S. No.

Query by

Queries regarding Tender No. PID(I)4020/24

Clarifications

1

Bidder A

LOT-1:
the electrical work at Dr site is complete with 150KVA Gen set and then again, it is mentioned 250KVA Gen set (Qty 2). Is it for Islamabad site or else. Need clarification on it.

Both are for DR site and follow the bidding document for specification.

2

Bidder B

LOT-1
Civil Work Data Center Facility
A thorough survey has been conducted of the site with regard to civil work for the preparation of Data Center Facility. Internal walls will have to be demolished to make room for the main Data Center Room as well as the Power Rooms and NOC etc.
The current condition of the roof is not good enough and there is a high risk that the roof may collapse during the demolishing of internal walls, and this could be very dangerous for the people working inside the building. Furthermore, due to the seepage inside the building the overall condition of the Facility has worsened.
Suggestion:
To avoid any further risk or damage to the building structure we suggest constructing a Greenfield Data Center in the space available within the same facility. The new facility will be built considering the Data Center standards and ideally the lifetime of the building will be much more as compared to the already existing building, which has a lot of issues.

DCF Facility will be reconstructed at the already designated place.

3

Bidder B

RFP Page 64 Section Rack: at point 15 Single / Three phase PDU is mentions as per the load. While at point 16, 32A three phase PDU is mentioned. Kindly confirm whether racks for MMR and Staging should also have 32A three phase PDU or 1P 32A PDU shall suffice.
Confirmation of the same is required.

Single phase 32A will be suffice.

4

Bidder B

RFP Page 65 Section 2.2: there is a contradiction in the statements at one point UPS 15 minutes backup is required on Full load, while on the same page it also mentions “Backup time required is 15 minutes runtimes at 70% load for each UPS Path.”
Confirmation with regards to battery backup at Full load or 70% load is required.

15 Minutes Backup required on full load.

5

Bidder B

No specific requirement of Precision In-row cooling units is mentioned in the RFP. Kindly confirm the rating of cooling units or the bidder can propose rating of cooling units on their own.

Precision cooling will be from the same vendor as DCF POD. Precision Cooling Units will be bidders responsibility to design as per the OEM recommendations.

6

Bidder B


RFP Page 67, section 2.6 (Inter Sites connectivity (Primary and DR) (Redundant)):
It is suggested to move this requirement into a separate LOT as this is related connectivity, since only few ISP have expertise for this requirement.

Please follow the bidding document.

7

Bidder C

Clarification on Clause 2.6 Reg arding Inter-Site Connectivity (Primary and DR) Page No 67 1. Internet & Data Circuit Requi rement: Quantity: 1 Nos ? a On e (01) x 100 Mbps internet con nection with three (03) usable IPv4 public IPs. o Two (02) x 1 00 Mbps data circuits betwee n NIMAR PR DC (PBC, Islamab ad) and DR located in Lahore. 2. Billing: o The above require ment is for the installation of i nternet & data circuits(PR/DR) with 3-year recurrent pricing b filling to be part of proposal ? 3. Payment Terms: o Will the p ayment of 3 years for internet & circuits be made in advance

Quote for the one year pricing.

8

Bidder B

RFP Page 68, Section 2.7: The specification of NOVEC 1230 based fire suppression system are mentioned. Kindly clarify the where the Suppression System is to be deployed i.e. Main Data Center Room, Power Rooms, MMR, Stagging room.

Fire suppression system is requried in all critical areasof DCF and should also conform Tier-3 standards.

9

Bidder C

1) Site Survey:
We would like to submit here that in order to submit the proposal for LOT No 1 there are major dependencies to design the solution.
Proposed DR site detailed proper survey is required by our technical teams in presence of your key team members, as we don’t know which premises / building is selected by you in Radio Pakistan Lahore compound. Without detailed technical survey of proposed building no one can design the appropriate solution.
Further Official pre-bid meeting is required to address technical queries of the bidders after the requested survey. arrange site survey
You are therefore requested to please schedule Site survey subsequently official Pre-Bid meeting where post site survey can be discussed for key solution offering.

2) Extension: Based on above request for such a crucial data center facility project we required minimum 3 to 4 weeks’ extension should be granted urgently.

we have already arranged site survey for the companies who had coordinated with us and requested for the site visit. We may arrange the same if request was received in due time.