|
S. No.
|
Obscure Name
|
Question
|
Answer
|
|
1
|
Bidder A
|
In Lot III item 1, Photocopier
machine your require 32CPM
A3 speed, its mean we have
to quote above 60 CPM
copier to meet this speed and
second please clarify that you
need Drum life 3 Million
copies or 300,000 copies. As
the heavy duty copiers have
extended drum life which
ensure lowest TCO.
|
1. The required specification is 36 CPM A4 and 18 CPM on A3.
2. Minimum drum life of 300,000 Copies
|
|
2
|
Bidder B
|
1. In LOT-III, Sr. No. 6.3.1, the
specifications mention 36 CPM at
A4 and 32 PPM at A3. This appears
to be a typographical error, as
photocopiers with 36 CPM at A4
typically offer only around 18–19
PPM at A3. We kindly request
clarification or correction of this
specification to avoid confusion
during evaluation.
2. The specified drum life of
300,000 pages is highly
brand-specific and not commonly
available through most authorized
distributors. We recommend either,
Removing drum life from technical
evaluation and instead requesting
cost per click, or Revising the
requirement to 100,000 pages,
which aligns with industry norms
and ensures fair, competitive
bidding.
3. Most 36 PPM (A4) copiers in this
category are equipped with up to
250 GB HDD. We suggest revising
the requirement to allow 128 GB
SSD or 250 GB HDD, which reflects
the typical configurations offered by
major brands.
4. We recommend allowing
item-wise quoting for LOT-III or
restructuring the lot accordingly.
|
1. The copying speed should be 36 cpm or higher on A4 and 18 cpm or higher on A3.
2. The minimum drum life of 100.000 Copies (This will supersede of clarification # 1(2)).
3. Please follow the bidding document
4. Please follow the bidding document
|
|
3
|
Bidder C
|
For turnkey solutions, we request
leniency in the marking criteria. This
clause alone carries 25 marks,
which is a significant portion of the
overall evaluation. Kindly consider
excluding this clause to ensure fair
and broader competition among
participants. Looking forward to
your favorable response.
|
1. Please Follow the bidding document
|
|
4
|
Bidder C
|
We need your guidance and
clarification on the following points
related to the IESCO load sanction
process:
Who will be responsible for
obtaining approval of the Load
Sanction from IESCO?
Who will deposit the Demand
Notice?
Who will deposit the Security?
Who will provide the Metering
Panel?
Is the pole with H-Type Frame
available on site?
Who will provide the HT Cables?
Additionally, we request an
extension of this bid at least 15
days.
Your timely response on these
matters will help us plan and
proceed accordingly.
|
1-3. Bidder will be responsible to complete all
the formalities with IESCO including, But not
limited to approval of sanction of load,demand
notice and security deposit.
4. Bidder will provide the metering panel and
is responsible for end to end deployment
5. No pole with H-Type frame is available on
site. Bidder will be responsible to arrange all
the items needed to fullfil the deployment
needs.
6. Bidder will provide HT Cables.
7. Please Follow the bidding document
|
| 5 | Bidder C | Rack A: 8-core splice Rack B: 8-core splice First Floor: 8-core splice
Query 1: The MMR is connected to Rack A and Rack B using 8+8 core splices. • Is this capacity sufficient for PR site requirements? • Can the same configuration be replicated at Dr site?
Query 2: The First Floor is connected to the MMR via an 8-core splice. • Is this sufficient for PR site requirements? • Should the same setup be mirrored at the DR site?
Query 3: 2. Power Plant to NetEco Server Connectivity A 4-port ODF is already installed and connected at both ends (Power Plant and NetEco Server). Is this configuration adequate for the PR site? Should the same be implemented at the DR site for consistency?
Query 4: NOC Connectivity The NOC is already connected to the switch installed in the Data Center. Is a separate ODF required in the NOC? If yes, please specify the destination or termination point for the other end of the ODF.
| 1. Yes the capacity is sufficent for Path A. There is no DR site mentioned in RFP. 2. No such requirements
3. We require a seprate path for PATH B
4. No such requirement
5. The ODF will be deployed on an as-need basis to ensure optimal connectivity where required. *These clarification responses are applicable to all bidders. |
| 6 | Bidder C | Query 5: Additional Connectivity If any other connectivity is required, please elaborate for both ends to ensure proper planning and implementation | Please follow the bidding document |
| 7 | Bidder C | Page 62 Item 11Bidder must provide the GA drawings of every proposed panel as per the proposed Single Line Diagram with details like Breaker Rating, Quantity of Components, internal spacing details. Cross sectional area and IEC 61439-1&2 standards-tested and compliant for greater safety, reliability and maintainability.Need to amend as local standards will be apply because these are not imported Types Tested panel and no Test report will be available. | Please follow the bidding document |
| 8 | Bidder C | Transformer PAD Mounted. Who will get approval of Load sanction from IESCO?
Who will deposit the Demand Notice ?
Who will Deposit Security? Who will provide Metering Panel?
Who will provide HT Cables?
What is Warranty on below Items as normally these items have One Year Warranty. AVR Gen Set Transformer Panel warranty. AVR IP 65 mentioned in RFP which will be required to Change in IP54. Need Clarification on Spare Parts Prices as mentioned on BID Page 31. Normally AVR comes with RS 485 Modbus so allow this as well. AVR response time mentioned in RFP 10M/s so allow 10m/s to 30m/s, as normally AVR Response time fall between 10-30m/s. Is customer has spare ports in Existing DCIM to configure new Equipment?
Page 61 11kv, 630Amps 4way switch with complete accessories. Need SLD and complete operational detail.
Page 61 Outgoing 45 x40A2-pole MCBs, 3phase &N Copper bus bars, Need SLD and complete operational detail. | 1. A pad-mounted transformer with canopy shall be preferred.
2-4. The bidder shall be responsible for completing all formalities with IESCO, including, but not limited to, the approval of load sanction, demand notice, and security deposit.
The bidder will provide the metering panel and is responsible for the end-to-end deployment.
No poles with H-Type frames are available on site. The bidder shall be responsible for arranging all items necessary to meet the deployment requirements.
The bidder will provide HT cables.
A one-year warranty is required; longer warranties will be advantageous to the bidder. Please follow the bidding document.
Please follow the bidding document. *These clarification responses are applicable to all bidders |
| 9 | Bidder C | Provision and installation of 01 Generator Sync panel, for 2x250KVA generators, completed in all respects: Specifications: a. Panel Outdoor/floor standing, powder coating, b. deepsea module, with auto phase reversal/failure protection, c. SPD, indication lamps and MOR (if required). MOR is dedicated build in or external MOR? Rating/Tier III need external type MOR for Gen-sets backup operations during the serviceability and maintainability period both including MTTR/MTBF etc, Kindly elaborate clearly? Expansion provision for future 3rd Genset and controller from day one? Over-All Electrical Single-Line-Diagram must be endorsed by CDCP or (CTDC) Certified Tier Design Consultant or (ATD) Accredited Tier Designer with having Experience of 10+ TIER III Data Centers Industry? | 1. External MOR will be prefered.
2. There is no such requiremnet of third genset please follow the bidding document.
3. Electrical SLD must be endorsed by a PEC-registered Electrical Engineer.
*These clarification responses are applicable to all bidders. |
| 10 | Bidder C | Page 61 Outgoing 45 x40A2-pole MCBs, 3phase &N Copper bus bars, Need SLD and complete operational detail with end point connectivity of device/load/nodes.? | The listed components shall be incorporated into the existing NIMAR SLD, and the updated SLD shall be provided. *These clarification responses are applicable to all bidders. |
| 11 | Bidder C | Could you please clarify what is meant by "set" in the quantities? We have noticed that the servers and network components do not have quantities mentioned, which is causing some confusion on our side. Kindly guide us so we can proceed accurately. | 1. The term “set” refers to a complete unit along with all required accessories and components necessary for its proper functionality. This definition applies uniformly to all items where the quantity is mentioned as set.
*These clarification responses are applicable to all bidders. |
| 12 | Bidder C | Dear Sir, For LOT 1 and LOT 3, certain items require a 1-year warranty. Could you please confirm whether the performance guarantee for these line items should also be for 1 year, or still for 3 years? | 1. The performance guarantee will be fixed as per lots. *These clarification responses are applicable to all bidders. |
| 13 | Bidder C | Technically for 400kVA AVR and required PMT Transformers, an upgraded system needed for 4C-185mm2 with 1C-5mm2 cables which seems surely under-sized cables for 400kVA system support. Correct operation of 400kVA system needs end to end upstream to downstream AVR onwards @240mm2-300mm2 Single core (5 including 4C + 1C Earth) is right sized approach, kindly advise the best? • Normally AVR comes with RS 485 Modbus dedicated built-in so allow this as well? • AVR response time mentioned in RFP 10M/s so allow 10m/s to 30m/s, as normally AVR Response time fall between 10-30m/s, allowed? • Do DCF have spare ports in Existing DCIM to configure new Equipment or that needs to be added from OEM as well as not mentioned anywhere as part and parcel of RFP? | 1. As per RFP, cable size shall be 4C-185mm² with ECC 1C-95mm².
2. Built-in RS-485 Modbus is acceptable in addition to SNMP for monitoring.
3. Response time shall be preferably 10ms but not exceeding 20ms.
4. Any additional modules, ports, or licenses required for DCIM integration shall be provisioned by the bidder. Please follow the bidding document
*These clarification responses are applicable to all bidders. |
| 14 | Bidder C | What is Warranty on below Items as normally these items have One Year Warranty? Or three Years including Critical Spares? o AVR o Gen Set o Transformer o Switchboards.
• AVR IP 65 mentioned in RFP which will be required to Change in IP54, please elaborate clearly?
• Need Clarification on Spare Parts Prices as mentioned on BID Page 31?
• As per Site, Existing Second ATS B is 400Amps up and running without any change needed, Change is only needed if it is needed to upgrade for suppling 400kVA AVR and 400kVA Transformer load support which means it needs end to end upgrade including contactor and Busbars/cubical including cables upgrade upto 600-800Amps system. Do the PATH B planning is shared or dedicated type for new induction of system for non-critical aux load? kindly confirm to avoid undercapacity planning at design phase from day one, right sizing is crux? | 1. Warranty shall be three (03) years including critical spares.
2. IP65 shall remain mandatory as specified in the RFP for outdoor environment protection.
3. It is a typographical error—Path-B AVR shall be 250 kVA with identical specifications and performance to Path-A.
*These clarification responses are applicable to all bidders. |
| 15 | Bidder C | • Transformer is PAD Mounted? Or Pole Mounted only?
• Always Dry-type / Oil Immersed PAD Mounting Transformer are recommended as per TIER III/Rating III conformance, if still need PMT (Pole mounted transformers),it should be used in dedicated Indoor placement in sub power house constructed room separately?
• Dedicated location of New Sub power-house for new Transformer constructed room separately?
• Separate Dedicated location of New Sub Metering Panel constructed room separately for new Transformer?
• How to comply TIER/RATED III Future design on upstream side for the existing Legacy old Path A shared Powerhouse and existing PMT Transformers arrangements without new dedicated additions as asked for PATH B?
o Who will get approval of Load sanction from IESCO?
o Who will deposit the Demand Notice ?
o Who will Deposit Security?
o Who will provide Metering Panel?
o Who will provide HT Cables? | 1. A pad-mounted dry-type transformer with canopy shall be preferred.
2. Possible locations have already been shared with bidders during the site survey; however, the final location remains subject to coordination with Radio Pakistan Electrical Team.
3. All other items will be provided by the biidder.
*These clarification responses are applicable to all bidders. |
| 16 | Bidder D | Please clarify as below as per INVITATION TO BIDS Bid Security: PKR 4M for Lot I PKR 6M for Lot II PKR 0.2M for Lot III But as per BDS page # 47 13. 18.1 The amount of Bid Security shall be fixed RKR 1 Million. Which one can be considerable? | 1. The figure mentioned in BDS page #47 is a typographical error. The correct Bid Security amounts are as stated
PKR 4 Million for Lot I
PKR 6 Million for Lot II
PKR 0.2 Million for Lot III
*These clarification responses are applicable to all bidders. |
| 17 | Bidder C | • Page 61 11kv, 630Amps 4way switch with complete accessories If its dedicated MV substation is needed? o MV substation replacement of existing legacy system with new sourcing Path A as well overall with addition of New B path? Which must come with MTTM and bus coupling feature for double bus bar system? External Bypass needed? Dedicated dual MV Power House Construction of Halls on compartmentalized approach separately? Is it surely needed to meet TIER/RATING III compliance in future? Please give us conceptual SLD and complete operational detail.? • Page 61 Outgoing 45 x40A2-pole MCBs, 3phase &N Copper bus bars, Need SLD and complete operational detail with end point connectivity of device/load/nodes.? | 1. Replacement of legacy MV substation is required.
2. Path-A shall remain unchanged, and a new path shall be established for Path-B.
3. Same place shown during site survey will be used.
4. Please follow the bidding document
5. External bypass required for maintainability.
6. Conceptual SLD shall be submitted by successful bidder |
| 18 | Bidder C | • Page 62 Item 11Bidder must provide the GA drawings of every proposed panel as per the proposed Single Line Diagram with details like Breaker Rating, Quantity of Components, internal spacing details. Cross sectional area and IEC 61439-1&2 standards-tested and compliant for greater safety, reliability and maintainability? • What about serviceability? • Need to allow local assembled of cubical(s) will be applied because these are not imported Types Tested panel and no Test report for Cubical is available.? | Please follow the bidding document |
| 19 | Bidder C | Dear Sir, We would like to request an extension for the submission, as there are several ground surveys still required. The passive survey has been completed; however, the power survey is still pending. We kindly seek your support in granting us an extension of at least 15 days to complete the remaining work and submit accordingly. Looking forward to your favorable response. | Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs |
| 20 | Bidder D | Dear Concern, We sincerely appreciate the opportunity to participate in this project. After carefully reviewing the requirements, our team is confident that we can design and deliver a robust, efficient, and future-ready solution tailored to your specific needs. Since our priority is to ensure the highest quality standards, we want to dedicate adequate time for in-depth analysis, solution design, and validation of all technical and commercial aspects. This will allow us to address your requirements comprehensively, minimize risks, and present a proposal that delivers maximum value and long-term benefits. In light of this, we kindly request an extension of two weeks to finalize and submit our proposal. We firmly believe this additional time will enable us to put forward the best possible solution aligned with your expectations. We truly value your support and understanding, and we remain committed to delivering excellence. | Bid submission date is
extended to Thursday 2nd October 2025 by 1100 Hrs |
| 21 | Bidder E | it is requested you to kindly extend bid submission date for 2 weeks | Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs |
| 22 | Bidder F | To conclude our proposal, our team visited on 17th Sept for Survey and found that still couple of clarifications like final location for placement of Gen Set, ATS and AVR yet to finalize by 19th Sep which are very critical for our input. Further certain equipment prices are still awaited from manufacturers. Would request you to extend the bidding time by 1 Week i.e. 29th September 2025. | Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs |
| 23 | Bidder G | We are pleased to participate in the subject tender for Procurement of IT Equipment. To prepare an accurate and competitive offer, we and our principal require additional time for special price approval. We kindly request an extension of the tender submission date by two weeks. We look forward to your consideration. | Bid submission date is extended to Thursday 2nd October 2025 by 1100 Hrs |
| | | |